NORTH DAKOTA STATE UNIVERSITY CME 240: FINANCIAL AND COST CONCEPTS FOR CMs. ASSIGNMENT # 4: (Due at 2:00 pm on April 9th, 2019. Question I: Your construction company worked on the projects shown in the table below during the last year. The duration shown in the table represents the number of months during the year that the project was under construction. Analyze the different profit centers based on their gross profit margins, their return on cash invested in the projects, and their use of management's time. One project manager can oversee three office remodel projects or one new building construction project 130 points Prof CenterRev G Average Monthly Investment (S) 37,500 25,000 27,500 23,000 20,000 24,000 Duration Months Office Remodel 150,000 Office Remodel 75,000 13,854 Office Remodel 55,000 New Building 375,000 41,659 New Building 325,000 New Building 270,000 22,272 10,120 35,555 32,338 NORTH DAKOTA STATE UNIVERSITY CME 240: FINANCIAL AND COST CONCEPTS FOR CMs. ASSIGNMENT # 4: (Due at 2:00 pm on April 9th, 2019. Question I: Your construction company worked on the projects shown in the table below during the last year. The duration shown in the table represents the number of months during the year that the project was under construction. Analyze the different profit centers based on their gross profit margins, their return on cash invested in the projects, and their use of management's time. One project manager can oversee three office remodel projects or one new building construction project 130 points Prof CenterRev G Average Monthly Investment (S) 37,500 25,000 27,500 23,000 20,000 24,000 Duration Months Office Remodel 150,000 Office Remodel 75,000 13,854 Office Remodel 55,000 New Building 375,000 41,659 New Building 325,000 New Building 270,000 22,272 10,120 35,555 32,338