Question
not gradedd pLEASE PROVIDE FORMULAS SO I UNDERSTAND Manufacturing Overhead Distribution Worksheet The following are selected operating data for the production and service departments of
not gradedd pLEASE PROVIDE FORMULAS SO I UNDERSTAND
Manufacturing Overhead Distribution Worksheet
The following are selected operating data for the production and service departments of Bluestone Company for 2016.
Departments | |||||
---|---|---|---|---|---|
Service | Production | ||||
1 | 2 | 1 | 2 | ||
Overhead costs (identified by department) | |||||
Indirect material | $96,800 | $164,400 | $50,880 | $1,032,000 | |
Indirect labor | $194,400 | $288,000 | $65,168 | $2,878,000 | |
Square feet of building floor space used | 9,600 | 14,400 | 24,000 | 48,000 | |
Assessed value of equipment used | $42,000 | $126,000 | $252,000 | $420,000 | |
Cubic yards of factory space used | 176,000 | 264,000 | |||
Machine hours | 102,400 | 409,600 | |||
Direct labor | $40,000 | $800,000 |
Building depreciation of $192,000 is allocated on the basis of square feet of floor space. Personal property taxes of $72,000 are allocated on the basis of assessed values of equipment used. Costs for service departments 1 and 2 are allocated to production departments on the basis of cubic yards of factory space and machine hours, respectively.
Required
a. Prepare a 2016 overhead distribution worksheet for Bluestone Company similar to the one prepared for Exhibit 3-15.
Use negative signs with answers, when appropriate. Under the Allocation Basis column, select the basis used to calculate each allocation.
Bluestone Company Overhead Distribution Worsksheet For the Year Ended December 31, 2016 | |||||
---|---|---|---|---|---|
Service Dept. 1 Dept. 2 | Production Dept. 1 Dept. 2 | Allocation Basis | |||
Directly identifiable with departments: | |||||
Indirect material | Answer
| Answer
| Answer
| Answer
| |
Indirect labor | Answer
| Answer
| Answer
| Answer
| |
Allocated to departments: | |||||
Building depreciation | Answer
| Answer
| Answer
| Answer
| AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
|
Personal property taxes | Answer
| Answer
| Answer
| Answer
| AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
|
Total overhead | Answer
| Answer
| Answer
| Answer
| |
Allocation of service departments: | |||||
Dept. 1 | Answer
| Answer
| Answer
| Answer
| AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
|
Dept. 2 | Answer
| Answer
| Answer
| Answer
| AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
|
Total allocated overhead | Answer
| Answer
| Answer
| Answer
|
b. Compute the manufacturing overhead rates for production departments 1 and 2 using machine hours and direct labor costs, respectively, for allocation bases.
Round answers to two decimal places, when applicable.
Production Dept. 1 | Answer
|
Production Dept. 2 | Answer
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started