Note that the project will be completed in six months. There is a two-month time lag in the schedule of monthly payment from the owner
- Note that the project will be completed in six months.
- There is a two-month time lag in the schedule of monthly payment from the owner to the general contractor.
- The owner hold 12% of monthly payment as retention money, but the general contractor cannot hold any retention from subcontract payment.
- Retention will be released over three months in equal amount (one third per month) after the completion of job.
- Monthly subcontract cost is 90% of value per month.
- There is a one-month time lag in the schedule of monthly payment from the general contractor to the subcontractors.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started