Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Notice at the court relied on an analogy in coming to a decision that the writing was insufficient. Is the analogy of strong? Yes or

Notice at the court relied on an analogy in coming to a decision that the writing was insufficient. Is the analogy of strong? Yes or no and why? Is there any other argument that the heritage might have made 13 compensation in this case? What values are in hand by this decision? Well values were given less weight by the judges in the decision?

image text in transcribed
HERITAGE CONSTRUCTORS, INC. v. CHRIETZBERG CASE 13-1 ELECTRIC, INC. AND RICHARD MARC CHRIETZBERG Court of Appeals of Texas, Sixth District 2015 Tex. App. LEXIS 1974 (2015) FACTS: In 2011, Heritage Constructors Inc., a general con- TexAmericas Center-East wastewater treatment plant improve- tractor that specializes in building water treatment plants, ment project. Heritage estimated that the project would take was preparing a bid to become the general contractor for the about 19 months to complete and intended to complete eighty to (continued) eighty-five percent of the project itself, but the project's electrical would have required more than a year to complete and thus work necessitated the use of a subcontractor. Before Heritage's fell under the statute of frauds. bid was due, Heritage was contacted by two electrical compa- Next, the Court had to determine whether the agreement nies attempting to bid on a subcontract for the electrical work. was enforceable under the statute of frauds. The Court Electrique Corporation bid $886,400 to perform electrical work found a precedent for this case in a similar case, Cohen v. on the project, and Chrietzberg Electric bid $704,857. With McCutchin. In that case, the United States Supreme Court Chrietzberg being the lower bidder, Heritage took that bid and had ruled that because there was no writing that identified included Chrietzberg on the bid to TexAmericas. TexAmericas the plaintiff as a party to the agreement in question, the eventually awarded the bid to Hertitage, and Heritage and agreement did not satisfy the statute of frauds. Similarly, in Chrietzberg congratulated each other on the successful bid. After the bid documents, which is where the agreement between receiving an executed contract from TexAmericas, Heritage Heritage and Chrietzberg supposedly laid, Chrietzberg was sent Chrietzberg a proposed subcontract. Shortly thereafter, not once mentioned as a party to the agreement. Heritage Chrietzberg notified Heritage that it was withdrawing its bid. also failed to point out any actions it took that are unequivo Heritage asked Chrietzberg to reconsider, without success, cally referable to its agreement with Chrietzberg. The agree- and so Heritage accepted Electrique's more expensive contract ment fell under the statute of frauds but failed to satisfy it, after accepting certain conditions of Electrique's. Heritage sued thus the Court ruled that Chrietzberg cannot be held liable Chrietzberg for breach of contract, promissory estoppel, and for breach of the agreement. negligent misrepresentation. The trial court ruled in favor of The Court then determined that there was no evidence Heritage, but awarded Heritage only twenty-eight percent of the that distinguished any of the damages supposedly caused fees it had asked for. Heritage appealed, and Chrietzberg cross- by breach from damage caused by promissory estoppel. appealed, claiming that all of Heritage's causes of action were Therefore, because Chrietzberg was not liable for breach dam- barred by the statute of frauds. ages, it was also not liable for promissory estoppel damages. Similarly, the negligent misrepresentation damages were indis- QUESTION: Were Heritage's claims of breach and prom- tinguishable from the other damages and so too were denied. issory estoppel invalid due to the statute of frauds? REASONING: This case primarily revolved around the DECISION: The Court reversed the trial court's ruling on Heritage's breach of contract and promissory estoppel requirement that contracts that cannot be completed in under a year must be in writing is The Court reviewed the claims and affirmed their denial of of negligent misrepre sentation claims. original project proposal, which indicated that the agree- ment between Heritage and Chrietzberg began December SIGNIFICANCE: This case exhibits the statute of frauds 31, 2011, and also indicated a projected project completion in action and demonstrates the significance of keeping all date of July 31, 2013. The Court ruled that the agreement important agreements in detailed writing

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law For Recreation And Sport Managers

Authors: Doyice J Cotten, John Wolohan

8th Edition

179244429X, 978-1792444296

More Books

Students also viewed these Law questions

Question

Values: What is important to me?

Answered: 1 week ago

Question

Purpose: What do we seek to achieve with our behaviour?

Answered: 1 week ago

Question

An action plan is prepared.

Answered: 1 week ago