Nova Company s total overhead cost at various levels of activity are presented below: Month Machine - Hours Total Overhead Cost April 4 7 ,

Nova Companys total overhead cost at various levels of activity are presented below:
Month Machine-Hours Total Overhead Cost
April 47,000 $ 186,490
May 37,000 $ 159,790
June 57,000 $ 213,190
July 67,000 $ 239,890
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is:
Utilities (variable) $ 55,500
Supervisory salaries (fixed)47,000
Maintenance (mixed)57,290
Total overhead cost $ 159,790
Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $239,890 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $239,890 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the companys total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 42,000 machine-hours?Nova Company's total overhead cost at various levels of activity are presented below:
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs
at the 37,000 machine-hour level of activity is:
Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
Estimate how much of the $239,890 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first
determine how much of the $239,890 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed
costs.)
Using the high-low method, estimate a cost formula for maintenance in the form Y=a+bx.
Express the company's total overhead cost in the form Y=a+bx.
What total overhead cost would you expect to be incurred at an activity level of 42,000 machine-hours?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Joe Hoyle, Thomas Schaefer, Timothy Doupnik

10th edition

0-07-794127-6, 978-0-07-79412, 978-0077431808

Students also viewed these Accounting questions