Nova Company's total overhead cost at vanous levels of activity are presented below: Month April Total Overhead Cost $195,000 $168, 100 $221, 900 $248,800 Machine Hours 50,000 40,000 60,000 70,000 May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 60,000 48,000 60, 100 $168, 100 Nova Company's management wants to break down the maintenance coit into its variable and fixed cost elements. Required: 1. Estimate how much of the $248,800 of overhead cost in July was maintenance cost. (Hint to do this, it may be helpful to first determine how much of the $248,800 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) hinhin mother artimnta anant from it for maintenannn in the form van 1. Estimate how much of the $248,800 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $248,800 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y a +bX. 3. Express the company's total overhead cost in the form Y = a +bX 4. What total overhead cost would you expect to be incurred at an activity level of 45,000 machine-hours? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Estimate how much of the $248,800 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $248,800 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) (Do not round intermediate calculations.) Maintenance cost in July Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bx. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.) Y ( Required Red > Express the company's total overhead cost in the form Y = a + bx. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.) Variable COST per Machine- Hour Fixed Cost Utilities cost Supervisory salaries cost Maintenance cost Total overhead cost Required 1 Required 2 Required 3 Required 4 What total overhead cost would you expect to be incurred at an activity level of 45,000 machine-hours? (Do not round intermediate calculations.) Total overhead costs