Nova Company's total overhead cost at various levels of activity are presented below: MonthMachine- HoursTotal Overhead CostApril45,000$165,300May35,000$142,700June55,000$187,900July65,000$210,500 Assume that the total overhead cost above consists
Nova Company's total overhead cost at various levels of activity are presented below:
MonthMachine-
HoursTotal
Overhead
CostApril45,000$165,300May35,000$142,700June55,000$187,900July65,000$210,500
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is:
Utilities (variable)$38,500Supervisory salaries (fixed)50,000Maintenance (mixed)54,200Total overhead cost$142,700
Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $210,500 of overhead cost in July was maintenance cost. ( it may be helpful to first determine how much of the $210,500 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the formY = a + bX.
3. Express the company'stotaloverhead cost in the formY = a + bX.
4. Whattotaloverhead cost would you expect to be incurred at an activity level of 40,000 machine-hours?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started