Nova Companys total overhead cost at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 54,000 $ 192,700 May 44,000 $

Nova Companys total overhead cost at various levels of activity are presented below:

Month Machine-Hours Total Overhead Cost
April 54,000 $ 192,700
May 44,000 $ 169,200
June 64,000 $ 216,200
July 74,000 $ 239,700

Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000 machine-hour level of activity is:

Utilities (variable) $ 48,400
Supervisory salaries (fixed) 46,000
Maintenance (mixed) 74,800
Total overhead cost $ 169,200

Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.

Required:

1. Estimate how much of the $239,700 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $239,700 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)

2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.

3. Express the companys total overhead cost in the form Y = a + bX.

4. What total overhead cost would you expect to be incurred at an activity level of 49,000 machine-hours?

1-

Estimate how much of the $239,700 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $239,700 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) (Do not round intermediate calculations.)

Maintenance cost in July
  • 2-

    Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)

    Y = +

    X

  • 3

    Express the companys total overhead cost in the form Y = a + bX. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)

    Variable Cost per Machine-Hour Fixed Cost
    Utilities cost
    Supervisory salaries cost
    Maintenance cost
    Total overhead cost $0.00 $0
    Y = + X
  • 4/

    What total overhead cost would you expect to be incurred at an activity level of 49,000 machine-hours? (Do not round intermediate calculations.)

    Total overhead cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cengage Learnings Online General Ledger For Heintz/parrys College Accounting, 2, 2 Terms (12 Months)

Authors: James A. Heintz, Robert W. Parry

22nd Edition

1305669991, 9781305669994

More Books

Students also viewed these Accounting questions