Question
Nova Companys total overhead cost at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 47,000 $ 194,340 May 37,000 $
Nova Companys total overhead cost at various levels of activity are presented below:
Month | Machine-Hours | Total Overhead Cost |
---|---|---|
April | 47,000 | $ 194,340 |
May | 37,000 | $ 167,140 |
June | 57,000 | $ 221,540 |
July | 67,000 | $ 248,740 |
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is:
Utilities (variable) | $ 59,200 |
---|---|
Supervisory salaries (fixed) | 48,000 |
Maintenance (mixed) | 59,940 |
Total overhead cost | $ 167,140 |
Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $248,740 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $248,740 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the companys total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 42,000 machine-hours?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started