Nova Companys total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 49,000 $ 200,220 May 39,000

Nova Companys total overhead cost at various levels of activity are presented below:

Month Machine- Hours Total Overhead Cost
April 49,000 $ 200,220
May 39,000 $ 176,420
June 59,000 $ 224,020
July 69,000 $ 247,820

Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is:

Utilities (variable) $ 46,800
Supervisory salaries (fixed) 70,000
Maintenance (mixed) 59,620
Total overhead cost $ 176,420

Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.

Required:

1. Estimate how much of the $247,820 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $247,820 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)

2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.

3. Express the companys total overhead cost in the form Y = a + bX.

4. What total overhead cost would you expect to be incurred at an activity level of 44,000 machine-hours?

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Estimate how much of the $247,820 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $247,820 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) (Do not round intermediate calculations.) Maintenance cost in July Required 1 Required 2 > Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bx. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.) Y = Required 1 Required 2 Required 3 Required 4 Express the company's total overhead cost in the form Y = a + bx. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.) Variable Cost per Machine - Fixed Cost Hour Utilities cost Supervisory salaries cost Maintenance cost Total overhead cost Y= Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 What total overhead cost would you expect to be incurred at an activity level of 44,000 machine-hours? (Do not round intermediate calculations.) Total overhead costs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image