Question
Nova Companys total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 54,000 $ 197,500 May 44,000
Nova Companys total overhead cost at various levels of activity are presented below:
Month | Machine- Hours | Total Overhead Cost | |||
April | 54,000 | $ | 197,500 | ||
May | 44,000 | $ | 172,000 | ||
June | 64,000 | $ | 223,000 | ||
July | 74,000 | $ | 248,500 | ||
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000 machine-hour level of activity is:
Utilities (variable) | $ | 61,600 |
Supervisory salaries (fixed) | 44,000 | |
Maintenance (mixed) | 66,400 | |
Total overhead cost | $ | 172,000 |
Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $248,500 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $248,500 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the companys total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 49,000 machine-hours?
- Required 1
1. Estimate how much of the $248,500 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $248,500 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) (Do not round intermediate calculations.)
|
- Required 2
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)
|
- Required 3
Express the companys total overhead cost in the form Y = a + bX. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)
|
- Required 4
What total overhead cost would you expect to be incurred at an activity level of 49,000 machine-hours? (Do not round intermediate calculations.)
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started