Question
Nova Companys total overhead cost at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 53,000 $ 203,600 May 43,000 $
Nova Companys total overhead cost at various levels of activity are presented below:
Month | Machine-Hours | Total Overhead Cost |
---|---|---|
April | 53,000 | $ 203,600 |
May | 43,000 | $ 180,600 |
June | 63,000 | $ 226,600 |
July | 73,000 | $ 249,600 |
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 43,000 machine-hour level of activity is:
Utilities (variable) | $ 47,300 |
---|---|
Supervisory salaries (fixed) | 66,000 |
Maintenance (mixed) | 67,300 |
Total overhead cost | $ 180,600 |
Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $249,600 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $249,600 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the companys total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 48,000 machine-hours?
Nova Company's total overhead cost at various levels of activity are presented below: Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 43,000 machine-hour level of activity is: Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $249,600 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $249,600 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y=a+bX. 3. Express the company's total overhead cost in the form Y=a+bX. 4. What total overhead cost would you expect to be incurred at an activity level of 48,000 machine-hours? Estimate how much of the $249,600 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $249,600 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) (Do not round intermediate calculations.) Using the high-low method, estimate a cost formula for maintenance in the form Y=a+bX. (Do not round your intermediate calculations. Round the "Variable cost per machine hour" to 2 decimal places.) Express the company's total overhead cost in the form Y=a+bX. (Do not round your intermediate calculations. Round the 'Variable cost per machine hour" to 2 decimal places.) What total overhead cost would you expect to be incurred at an activity level of 48,000 machine-hours? (Do not round intermediate calculations.)Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started