Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Now assume the owner caused a delay of three days in the start of activity E (so it starts on its original late dates).
Now assume the owner caused a delay of three days in the start of activity E (so it starts on its original late dates). The owner can use the argument that activity E had three days of total float, thus the contractor does not qualify for time extension or compensation (see Figure 13.4). The contractor argues that this delay will force it either to hire a second crew on days 20, 21, and 22 or finish the project three days late. For this reason, the contractor requests additional compensation and/or time exten- sion for 3 days. 35 The answer to this argument generally lies in the contract agreement. If the contractor granted the owner ownership of the float, the owner can use the float to absorb any delay. If the contractor has ownership of float, he may be entitled to time extension or compensation if he can prove that the delay disrupted his resource allocation plan, even though it affected a noncritical activity and did not delay the entire project (see Figures 13.5 to 13.7).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started