Question
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this
NPVs, IRRs, and MIRRs for Independent Projects
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows:
Year Truck Pulley
1 $5,100 $7,500
2 $5,100 $7,500
3 $5,100 $7,500
4 $5,100 $7,500
5 $5,100 $ 7,500
- Calculate the IRR for each project. Round your answers to two decimal places.
Truck: %
- What is the correct accept/reject decision for this project?
- -Select-
Accept
Reject
Pulley:%
- What is the correct accept/reject decision for this project?
-Select-
Accept
Reject
- Calculate the NPV for each project. Round your answers to the nearest dollar, if necessary. Enter each answer as a whole number. For example, do not enter 1,000,000 as 1 million.
Truck: $
- What is the correct accept/reject decision for this project?
Select-
- Accept
- Reject
- Pulley: $
- What is the correct accept/reject decision for this project?
- -Select-
- Accept
- Reject
- Calculate the MIRR for each project. Round your answers to two decimal places.
Truck:%
- What is the correct accept/reject decision for this project?
- Accept
- Reject
- Pulley:%
What is the correct accept/reject decision for this project?
- Accept
- Reject
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started