number 2: please show how Assume a company charges time and material. The labor charge for a job was $50 per hour and the parts
number 2: please show how
Assume a company charges time and material. The labor charge for a job was $50 per hour and the parts and material was 417 and the material loading charge was 50%. The job took 16 hours to complete. Rounding to the nearest two decimal places, what did the company charge for this job?