Question

1 Approved Answer

Number 9: Determine the total estimated cost at completion of the project and the variance for each cost code Only problem number 9 then broken

Number 9: Determine the total estimated cost at completion of the project and the variance for each cost code

image text in transcribedOnly problem number 9

image text in transcribedimage text in transcribed

then broken down into cost codes. Sample cost codes lul d COST CODES: Code Description 01000 GENERAL REQUIREMENTS 01100 Supervision 01400 General Labor 01600 Temporary Facilities 01700 Temporary Utilities 01800 Temporary Phone 01900 Clean-Up Code Description 09000 FINISHES 09050 Metal Studs 09100 Drywall 09200 Ceramic Tile 09300 Acoustical Treatment 09400 Carpet & Vinyl 09800 Paint 09850 Wall Coverings 02000 EXISTING CONDITIONS 02050 Demolition 10000 SPECIALTIES 10400 Signage 10700 Toilet Partitions 10800 Toilet & Bath Accessories 03000 CONCRETE 03200 Under-slab Gravel 03300 Footing&Found.-Labor 03400 Footing & Found.-Cond. 03450 Concrete Pump 03500 Slab/Floor-Labor 11000 EQUIPMENT 11100 Appliances 03600 Slab/Floor-Concrete 03650 Light-Weight Concrete 03700 Pre-cast Concrete 03900 Rebar 12000 FURNISHINGS 12300 Cabinetry & Counter Tops 12350 Counter Tops 12500 Window Treatments 04000 MASONRY 04100 14000 CONVEYING SYSTEMS 14100 Elevators 05000 METALS 05100 Structural Steel 05300 Joist & Deck 05400 Misc. Steel 05900 Erection 20000 FIRE SUPPRESSION 21100 Fire Sprinklers 22000 PLUMBING 22100 Plumbing 06000 06110 06120 WOOD, PLASTICS, & COMP Rough Carpentry Lumber 23000 HVAC 23100 HVAC 23200 Gas Lines 06210 Finish Carpentry 26000 ELECTRICAL 26100 Electrical 07000 THERMAL & MOIST. PROT 07100 Waterproofing 07200 Insulation 07210 Foundation Insulation 07250 Fireproofing 07300 Stucco 31000 EARTHWORK 31100 Grading & Excavation 07450 Rain Gutters 07500 Roofing 07600 Flashings-Sheet Metal 07700 Roof Specialties 07900 Caulking & Sealants 32000 EXTERIOR IMPROVWEMENTS 32100 Asphalt 32200 Site Conc.-Labor 32300 Site Conc.-Concrete 32400 Signage 32500 Landscaping 32600 Dumpster Enclosures 32900 Outside Lighting 08000 OPENINGS 08110 Metal Doors & Frames 08200 Wood Doors 08300 Overhead Doors 08400 Store Fronts 08700 Hardware 08800 Glass & Glazing 33000 UTILITIES 33200 Water Line 33500 Power Lines 33600 Telephone Lines FIGURE 2-6 Sample Cost Codes for a Commercial Contractor

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Lakeside Company Case Studies In Auditing

Authors: John Trussel, J. Douglas Frazer

12th Edition

0132567253, 978-0132567251

More Books

Students also viewed these Accounting questions