O 1 . Determine the duration of project for the activities shown below, and find the critical path by using Gantt chart table [

O1.
Determine the duration of project for the activities shown below, and find the critical path by using Gantt chart
\table[[Activity,A,B,C,D,E,F,O,H,I,J,K,M,N,R],[\table[[Duration],[(Weeks)]],3,3,4,5,2,6,5,8,3,5,1,6,8,2],[Predecessor,-,A,A,A,B,D,-,-,C,H,D,I,O,M,I]]
Q2.
Create the (AON) diagram of the below table which indicate the activities and their precedence activity as well as their duration, also find out the critical path
\table[[Activity,Precedence,Duration],[A,-,2],[B,-,3],[C,A,2],[D,A,B,4],[E,C,4],[F,C,3],[G,D,E,5],[H,G,F,2]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Restaurant From Concept to Operation

Authors: John R Walker

6th Edition

9781118139950, 470626437, 111813995X, 978-0470626436

Students also viewed these General Management questions

Question

xarah, inc.

Answered: 1 week ago