O Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Quantity and cost 6 pounds e $9 per pound 3 DLH e $17 per DLH 3 DLH $12 per DLH Actual Results 47,900 pounds @ $9.10 per pound 23,300 hours & $17.50 per hour $ 290,600 7,900 units (1) Prepare the standard cost card showing standard cost per unit. (2) Compute total budgeted cost for June production (3) Compute total actual cost for June production (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Prepare the standard cost card showing standard cost per unit. Direct materials Direct labor Overhead Total S Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Quantity and cost 6 pounds $9 per pound 3 DLH $17 per DLH 3 DLE $12 per DLH Actual Results 47,900 pounds e $9.10 per pound 23,300 hours $17.50 per hour $ 290,600 7,900 units ces (1) Prepare the standard cost card showing standard cost per unit. (2) Compute total budgeted cost for June production (3) Compute total actual cost for June production. (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute total budgeted cost for June production. Total budgeted (standard) cout Required information The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Quantity and Cost 6 pounds e $9 per pound 3 DLH $17 per DLH 3 DLH $12 per DLH Actual Results 47,900 pounds @ $9.10 per pound 23,300 hours @ $17.50 per hour $ 290,600 7,900 units ces (1) Prepare the standard cost card showing standard cost per unit. (2) Compute total budgeted cost for June production, (3) Compute total actual cost for June production (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute total actual cost for June production, Actual cost Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Quantity and cost 6 pounds & $9 per pound 3 DLH @ $17 per DLH 3 DLH $12 per DLH Actual Results 47,900 pounds @ $9.10 per pound 23,300 hours @ $17.50 per hour $ 290,600 7,900 units (1) Prepare the standard cost card showing standard cost per unit (2) Compute total budgeted cost for June production, (3) Compute total actual cost for June production (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required i Required 2 Required 3 Required 4 Compute total cost variance for June. (Indicate the effect of the variance by selecting favorable, unfavorable, or no varian Total con variance