Odette Manufacturing produces three products: Widget A, Widget B, and Widget C The following information is available for each product. A B C Direct material
Odette Manufacturing produces three products: Widget A, Widget B, and Widget C The following information is available for each product.
| A | B | C |
Direct material cost per unit | $2.00 | $8.00 | $10.00 |
Direct labor cost per hour | $15.00 | $16.75 | $18.00 |
Odette Manufacturing presently applies overhead using a predetermined rate based on direct labor hours. Estimated Direct Labor hours for the year are 132,026.
The product leader for Widget B has suggested that Odette Manufacturing switch to activity-based costing and identified the following activities, cost drivers, estimated costs, and estimated cost driver units for the year:
Activity | Recommended Cost Driver | Estimated Cost | Estimated Cost DriverUnits |
Ordering Cost | Purchase Orders | $33,912 | 1256 Purchase Orders |
Machine Operations | Machine Hours | $1,425,000 | 12500 Hours |
Environmental Compliance | Compliance Test | $125,400 | 110 Test |
| Total OH Cost | $1,584,312 |
|
| Actual January Production | ||
| A | B | C |
Number of Units Produced | 5,875 | 7,200 | 5,800 |
Direct Labor Hours | 3,150 | 4,100 | 4,250 |
Machine Hours | 375 | 206 | 442 |
Compliance Test | 2 | 3 | 5 |
Purchase Orders | 14 | 19 | 15 |
Using ABC how much ordering Environmental Compliance cost is allocated to Widget B?
a. | $3,420 | |
b. | $23,484 | |
c. | $1,140 | |
d. | $5,700 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started