Office Automation Inc., has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular
- Office Automation Inc., has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be accomplished in order to complete the new office system project. Information about the activities is shown in the table below. Times are in weeks.
Data for Office Automation, Inc. (Times are given in days) | ||||||
Activity | Description | Immediate Predecessors | Normal Time | Crash Time | Normal Cost ($) | Crash Cost ($) |
A | Plan needs | ----------- | 10 | 8 | 30 | 70 |
B | Order equipment | A | 8 | 6 | 120 | 150 |
C | Install equipment | B | 10 | 7 | 100 | 160 |
D | Set up training lab | A | 7 | 6 | 40 | 50 |
E | Training course | D | 10 | 8 | 50 | 75 |
F | Testing system | C, E | 3 | 3 | 60 | ------- |
a). Show the network for the project.
b). Develop an activity schedule for the project using normal times.
c). What are the critical path activities and what is the expected project completion time?
2.- Use the Trial and Error Method to solve problem 1 to crash 2 days of the project network. What is the Total Cost of Crashing including the Normal Cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started