Question
Old Fogey Inc entered into a long-term construction contract to build a Retirement Home exclusively for former HU faculty who are slightly more effective on
Old Fogey Inc entered into a long-term construction contract to build a Retirement Home exclusively for former HU faculty who are slightly more effective on the golf course (which isnt too much) than the classroom.
Old Fogey Inc elects to apply the percent of completion method to all long-term contracts.
The contract price is set at $5,800,000 and additional information is as shown:
2020 2021 2022
Cost spent to date $ 840,000 $3,080,000 $4,300,000
Additional Estimated costs to complete 3,360,000 1,320,000 0
Progress Billings $900,000 $3,400,000 $1,100,000
Cash collected 750,000 2,750,000 1,900,000
REQUIRED: Show your work
- Determine the amount of revenue and profit that will be recognized in 2020, 2021 and 2022 respectively.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started