Question
Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical
Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical data suggest 5 function points equal one person-month and 6 people can work on the project. (Round answers to the nearest whole numbers.)
Complexity Weight Table | ||||
Number of inputs | 10 | Rated complexity | low | 2 points |
Number of outputs | 19 | Rated complexity | average | 7 points |
Number of inquiries | 9 | Rated complexity | average | 5 points |
Number of files | 27 | Rated complexity | high | 10 points |
Number of interfaces | 60 | Rated complexity | high | 17 points |
a. The total function point count is:
b. Calculate the estimated project duration:
c. If 8 people are available for the project, what is the estimated project duration?
d. If the project must be complete in six months, how many people will be needed for the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started