Question

1 Approved Answer

On a Wednesday 5 pm, the facility air conditioning suffered fire damage. The optimistic (O), most likely (M), and pessimistic (P) times of the activities

On a Wednesday 5 pm, the facility air conditioning suffered fire damage. The optimistic (O), most likely (M), and pessimistic (P) times of the activities of its repair project are shown in the table below. Work hours are 8 am to 5 pm Monday through Friday.

If the repair job commenced at 8 am on Thursday, the day and time of its expected completion, the probabilities that the project would be completed in duration of a) four workdays and b) six workdays, respectively, are:

image text in transcribed
Predecessor O, M, Activity P, hours activity hours hours 1: Report, clean up, test, order parts 6 8 12 2: Review higher-up's inputs/approval 4 24 36 3: Assemble replacement parts 1 3 6 9 4: System leak check and test 2, 3 6 9 11 5: Draft repair report and document 1 2 4 6 6: 2nd test and fill data in the report 5 2 4 6 7: Submit report, bills, process payment 4, 6 4 7 12

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Restaurant Concepts, Management, And Operations

Authors: John R Walker

8th Edition

1119393582, 9781119393580

More Books

Students also viewed these General Management questions

Question

2. Ask questions, listen rather than attempt to persuade.

Answered: 1 week ago