On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work commenced on June 1, 2018, and it is expected

On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work commenced on June 1, 2018, and it is expected to continue through May 31, 2019. Powell made progress payments to the contractor in 2018 as follows:

Date

Amount

June 1

$ 123,000

July 1

174,000

September 1

81,000

November 1

33,000

$411,000

As stated previously, Powell took a 1-year, 8%, $175,000 construction loan to help fund the work on this project. The company also has a 4-year, 5%, $654,350 loan that is not related to the construction project.

Give the adjusting entry needed at December 31, 2018 to record the capitalization of interest for this project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting And Finance For Non-Specialists

Authors: Eddie McLaney, Peter Atrill

3rd Edition

9780273646327

More Books

Students also viewed these Accounting questions

Question

Why must in-service training or on-the-job education be continuing?

Answered: 1 week ago