Question
On December 31 of the current year, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a
On December 31 of the current year, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State Construction anticipates the construction will take three years. The companys accountants provide the following contract details relating to the project:
Contract price | $624 | million |
Estimated construction costs | $480 | million |
Estimated total profit | $144 | million |
During the three-year construction period, State Construction incurred costs as follows:
Year 1 | $48 | million |
Year 2 | $288 | million |
Year 3 | $144 | million |
State Construction uses the cost-to-cost method to recognize revenue. Which of the following represent the revenue recognized in Year 1, Year 2, and Year 3?
Select one:
a. $62 million, $374 million, $187 million
b. $62 million, $312 million, $250 million
c. None of these are correct.
d. $60 million, $376 million, $188 million
e. $0 million, $0 million, $624 million
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started