Question
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: 2014 2015 2016 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000 Collections to date 2,000,000 3,500,000 5,500,000
Instructions Fill in the correct amounts on the following schedule.For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2010, 2011, and 2012.
Percentage-of-Completion Revenue
2010:
2011:
2012:
Completed-Contract Revenue
2010:
2011:
2012:
Percentage-of-Completion Gross Profit
2010:
2011:
2012:
Completed-Contract Gross Profit
2010:
2011:
2012:
Calculate the Over/Under Billing for:
2010:
2011:
2012:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started