Question
On February 1, 2014, Nelson Corporation purchased a parcel of land as a factory site for $231,036. An old building on the property was demolished,
On February 1, 2014, Nelson Corporation purchased a parcel of land as a factory site for $231,036. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2014. Costs incurred during this period are listed below:
Demolition of old building $22,578
Architect's Fees $31,413
Legal fees for title investigation and purchase contract $4,957
Construction Costs $1,281,829 Salvaged materials resulting from demolition were sold for $10000
The company also spent $2,071 to fence the property. What is the cost of the Building?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started