On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished
On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:
2020 2021 2022
Total costs incurred to date $8,000 $10,000 $22,000
Estimated costs to complete 12,000 6,000 -0-
Customer billings to date 8,000 24,000 29,000
Collections to date 4,000 14,000 25,000
The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started