On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished

On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:

2020 2021 2022

Total costs incurred to date $8,000 $10,000 $22,000

Estimated costs to complete 12,000 6,000 -0-

Customer billings to date 8,000 24,000 29,000

Collections to date 4,000 14,000 25,000

The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tax Accounting

Authors: Greg Shields

1st Edition

163716128X, 978-1637161289

More Books

Students also viewed these Accounting questions

Question

2. Does the organisation take a process perspective?

Answered: 1 week ago