On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished,

On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below:

Demolition of old building $ 21000
Architect's fees 36000
Legal fees for title investigation and purchase contract 5300
Construction costs 1392000
(Salvaged materials resulting from demolition were sold for $10800.)

Crane should record the cost of the land and new building, respectively, as

$328200 and $1433300.

$328200 and $1428000.

$344300 and $1417200.

$333500 and $1428000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: John Hoggett, Lew Edwards, Evelyn Hogg, John Medlin, Matthew Tilling

8th Edition

1742466362, 978-1742466361

More Books

Students also viewed these Accounting questions

Question

what is the best upper bound growth rate for 5n+2

Answered: 1 week ago

Question

Cite the reasons employees join unions.

Answered: 1 week ago