Question

1 Approved Answer

On February 1, 2020, Sunland Contractors agreed to construct a building at a contract price of $5,810,000. Sunland estimated total construction costs would be $4,008,000

On February 1, 2020, Sunland Contractors agreed to construct a building at a contract price of $5,810,000. Sunland estimated total construction costs would be $4,008,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:

2020 2021 2022
Total costs incurred to date $1,503,000 $2,646,000 $4,605,000
Estimated costs to complete 2,505,000 1,764,000 -0-
Customer billings to date 2,210,000 4,008,000 5,610,000
Collections to date 2,010,000 3,510,000 5,510,000

Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2020, 2021, and 2022.

Percentage-of-Completion Gross Profit Completed-Contract Gross Profit
2020 $

2020 $

2021 $

2021 $

2022 $

2022 $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Accounting And Multinational Enterprises

Authors: Lee H. Radebaugh, Sidney J. Gray

4th Edition

0471056014, 978-0471056010

More Books

Students also viewed these Accounting questions

Question

Give an example of a high-level programming language.

Answered: 1 week ago