Question

1 Approved Answer

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2021,

image text in transcribed

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2021, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of $3,820,000 were incurred. The company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion. Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method. 20. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred). 2b. Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred). 30. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022 Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 28 Req 3A Req 3B Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Round your final answers to the nearest whole dollar.) Percentages of completion Choose numerator Actual costs to date Choose denominator Estimated total costs = % complete to date 2021 $ 2,020,000+ 6,040,000 = 2022 $ 4,540,000+ $ 8,170,000 = 2023 $ 8,360,000 $ 8,360,000 33.4437% 55.5692% 100.0000% 2021 To date Recognized in prior years Recognized in 2021 Construction revenue S 2,695,562 $ 0 $ 2,695,562 Construction expense Gross profit (loss) $ 2,020,000 S 0 $ 2,020,000 S 675,562 $ 0 $ 675,562 2022 To date Recognized in prior years Recognized in 2022 Construction revenue $ 4,478,877 $ 2,695,562 $ 1,783,315 Construction expense $ 2,020,000 $ (2,020,000) Gross profit (loss) $ 675,562 $ (675,562) 2023 To date Construction revenue $ Construction expense $ 8,060,000 8,360,000 $ Gross profit (loss) $ (300,000) Recognized in prior years Recognized in 2023 4,478,877 $ 3,581,123 $ 8,360,000 $ (300,000)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Donald E. Kieso, Jerry J. Weygandt, and Terry D. Warfield

15th edition

978-1118159644, 9781118562185, 1118159640, 1118147294, 978-1118147290

Students also viewed these Accounting questions

Question

solve b. 3 tan 0 cos 0 - de

Answered: 1 week ago

Question

What are the 5 Cs of marketing channel structure?

Answered: 1 week ago

Question

Where did you not get as far as you wanted?

Answered: 1 week ago

Question

What would be useful to you today from this experience?

Answered: 1 week ago

Question

What do you remember positively about it? What negatively?

Answered: 1 week ago