On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,600,000. During 2021, costs
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,600,000. During 2021, costs of $2,200,000 were incurred with estimated costs of $4,200,000 yet to be incurred. Billings of $2,700,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,700,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2,950,000 and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of $4,000,000 were incurred. The companys fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022.
Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021. (Do not round intermediate calculations. Round your answers to the nearest dollar amount.)
|
Complete this question by entering your answers in the tabs below.
- Req 1
- Req 2A
- Req 2B
- Req 3A
- Req 3B
Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022. (Do not round intermediate calculations. Round your answers to the nearest dollar amount.)
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started