Question

1 Approved Answer

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,275,000. During 2021, costs

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,275,000. During 2021, costs of $2,110,000 were incurred, with estimated costs of $4,110,000 yet to be incurred. Billings of $2,632,000 were sent, and cash collected was $2,360,000. In 2022, costs incurred were $2,632,000 with remaining costs estimated to be $3,765,000. 2022 billings were $2,882,000, and $2,585,000 cash was collected. The project was completed in 2023 after additional costs of $3,910,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred). 2b. Prepare journal entries for 2022 to record the transactions described (credit "various accounts for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022. Req 1 Req 2A Req 2B Req Req 3B Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. (Loss amounts should be indicated with a minus sign.) Year Revenue Gross profit (loss) recognized recognized $ 0 $ 2021 0 2022 0 2023 8,275,000 $ 8,275,000 $ Total 0 Reg 1 Req 2A Reg 2B Req Reg 3B Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.) No Year General Journal Debit Credit 1 2022 Construction in progress 2,632,000 Various accounts 2,632,000 2 2022 2,882,000 Accounts receivable Billings on construction contract 2,882,000 2022 Cash 2,585,000 Accounts receivable 2,585,000 4 2022 Billings on construction contract Req 1 Reg 2A Reg 2B Reg Reg 3B Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022. (Do not round intermediate calculations. Round your answers to the nearest dollar amount.) Balance Sheet At December 31, 2022 Current assets: Accounts receivable 569,000 Current liabilities: Billings in excess of costs x $ 772,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ISO 13485 Auditing Journal Notes Checklists Observations Evidence Log

Authors: Just Visualize It, The Quality Guy

1st Edition

B08W7SNPGP, 979-8706121884

More Books

Students also viewed these Accounting questions

Question

Presentations Approaches to Conveying Information

Answered: 1 week ago