On January 1, 2014, BRANDON INGRAM Construction Corporation began constructing a P 2,100,000 contract. The following are relevant information provided by the corporation. BRANDON INGRAM

On January 1, 2014, BRANDON INGRAM Construction Corporation began constructing a P 2,100,000 contract. The following are relevant information provided by the corporation. BRANDON INGRAM uses percentage of completion method. For the year ended December 31, 2015, BRANDON INGRAM billed its client an additional 55% of the contract price.

2014 2015 2016

Construction in Progress 441,000 ? ?

Estimated costs to complete ? ? ?

Costs Incurred 425,250 969,000 675,750

Excess of CIP over PB 84,000 CL 330,750 CL

1. How much is the estimated remaining cost in 2014?

2. How much is the realized gross profit (loss) in 2015?

3. How much is the balance of construction in progress in 2015?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting

Authors: Late RC Sekhar, AV Rajagopalan

1st Edition

195683609, 978-0195683608

More Books

Students also viewed these Accounting questions

Question

1. Information that is currently accessible (recognition).

Answered: 1 week ago