On January 1, 2014, X signed contract to build a bridge at a price of Tk. 30,00,000. As the client was very happy to see

On January 1, 2014, X signed contract to build a bridge at a price of Tk. 30,00,000. As the client was very happy to see the finished building, they have allowed Tk.50,000 as bonus, in addition to the settled contract price. The following information pertains to the construction period.

2014 2015

Costs incurred to date $8,88,000 $24.88,000

Estimated costs to complete $15,12,000 0

Progress billing to date $850,000 $30,50,000

Collections to date $800,000 $30,50,000

Instructions: prepare all necessary journal entries and partial balance sheet for 2014 - 2015 in your script.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cornerstones of Managerial Accounting

Authors: Maryanne Mowen, Don Hanson, Dan Heitger, David McConomy, Bradley Witt, Jeffrey Pittman

3rd Canadian edition

176530886, 176721231, 978-0176721237

More Books

Students also viewed these Accounting questions

Question

2. Information that comes most readily to mind (availability).

Answered: 1 week ago

Question

3. An initial value (anchoring).

Answered: 1 week ago

Question

4. Similarity (representativeness).

Answered: 1 week ago