On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows:
2018 | 2019 | 2020 | |
Total costs incurred to date | $1,500,000 | $3,300,000 | $4,400,000 |
Estimated costs to complete | 2,500,000 | 1,000,000 | -0- |
Customer billings to date | 1,200,000 | 2,700,000 | 4,400,000 |
Collections to date | 1,000,000 | 2,500,000 | 4,400,000 |
Instructions: Assuming the building was finished in 2020, calculate the gross profit that would be recorded for 2018, 2019 and 2020 using the: a) Completed contract method. b) Percentage of completion method.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started