On January 1, 2018, T Limited signed contract to construct a bridge at a price of Tk. 25,00,000. At the end of the construction, because

On January 1, 2018, T Limited signed contract to construct a bridge at a price of Tk. 25,00,000. At the end of the construction, because of a minor construction defect, the client has decided to deduct Tk. 25,000 according to a clause of the contract. The following information pertains to the construction period. 2018 2019 2020 Costs incurred during the year Estimated costs yet to be incurred Customer billings during the year Collection of billing during the year Tk. 6,00,000 14,00,000 5,00,000 4,00,000 Tk. 9,60,000 3,90,000 10,00,000 9,00,000 Tk. 11,40,000 0 9,75,000 11,50,000 Instructions: Prepare necessary journal entries for 2018 - 2020 and partial balance sheet (only for 2018).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting For Decision Makers

Authors: Mark DeFond

2nd Edition

1618533142, 9781618533142

More Books

Students also viewed these Accounting questions

Question

=+ What are the undesirable consequences?

Answered: 1 week ago

Question

Explain the pages in white the expert taxes

Answered: 1 week ago