Question

1 Approved Answer

On January 1, 2020, Curtis Construction Ltd. started a construction project for $ 4,500,000. Relevant data for 2020 and 2021 are as follows: 2020 2021

On January 1, 2020, Curtis Construction Ltd. started a construction project for $ 4,500,000. Relevant data for 2020 and 2021 are as follows:

2020 2021 Current year construction costs $ 3,300,000 $ 620,000 Estimated remaining costs to complete 600,000 -0- Current year billings 3,100,000 1,400,000 Current year collections 3,000,000 1,500,000

Required:

  1. For 2020 and 2021, calculate the following for both the completed contract and percentage of completion method (8 marks):
  1. Gross Profit
  2. Construction in progress year end balance
  3. Cost in excess of billings (Billings in Excess of Costs)
  1. Briefly explain when the completed contract method would be used instead of the percentage of completion (2 marks).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sound Investing, Chapter 19 - Related-Party Transaction Ruse

Authors: Kate Mooney

1st Edition

0071719415, 9780071719414

More Books

Students also viewed these Accounting questions

Question

Understand human resource planning in an academic setting.

Answered: 1 week ago

Question

Analyze mentoring and career planning opportunities for academics.

Answered: 1 week ago