Question
On January 1, 2020, Martinez Corporation purchased for $620,000 a tract of land (site number 101) with a building. Martinez paid a real estate broker's
On January 1, 2020, Martinez Corporation purchased for $620,000 a tract of land (site number 101) with a building. Martinez paid a real estate broker's commission of $44,640, legal fees of $7,440, and title guarantee insurance of $22,320. The closing statement indicated that the land value was $620,000 and the building value was $124,000. Shortly after acquisition, the building was razed at a cost of $66,960.
Martinez entered into a $3,720,000 fixed-price contract with Slatkin Builders, Inc. on March 1, 2020, for the construction of an office building on land site number 101. The building was completed and occupied on September 30, 2021. Additional construction costs were incurred as follows.
Plans, specifications, and blueprints $26,040
Architects' fees for design and supervision 101,680
The building is estimated to have a 40-year life from date of completion and will be depreciated using the 150% declining-balance method.
To finance construction costs, Martinez borrowed $3,720,000 on March 1, 2020. The loan is payable in 10 annual installments of $372,000 starting on March 1, 2021, plus interest at the rate of 10%. Martinez's weighted-average amounts of accumulated building construction expenditures were as follows.
For the period March 1 to December 31, 2020 $1,612,000
For the period January 1 to September 30, 2021 2,356,000
(a)
a schedule that discloses the individual costs making up the balance in the land account in respect of land site number 101 as of September 30, 2021.
MARTINEZ CORPORATION
Cost of Land (Site #101)
As of September 30, 2021
Cost of Land and Old Building
$620,000
Real Estate Broker's Commission
44,640
Legal Fees
7,440
Title Insurance
22,320
Removal of Old Building
66,960
Cost of Land
$761,360
(b)
a schedule that discloses the individual costs that should be capitalized in the office building account as of September 30, 2021.
MARTINEZ CORPORATION
Cost of Building
As of September 30, 2021
$
$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started