Question

1 Approved Answer

On January 1, 2020, Martinez Corporation purchased for $620,000 a tract of land (site number 101) with a building. Martinez paid a real estate broker's

On January 1, 2020, Martinez Corporation purchased for $620,000 a tract of land (site number 101) with a building. Martinez paid a real estate broker's commission of $44,640, legal fees of $7,440, and title guarantee insurance of $22,320. The closing statement indicated that the land value was $620,000 and the building value was $124,000. Shortly after acquisition, the building was razed at a cost of $66,960.

Martinez entered into a $3,720,000 fixed-price contract with Slatkin Builders, Inc. on March 1, 2020, for the construction of an office building on land site number 101. The building was completed and occupied on September 30, 2021. Additional construction costs were incurred as follows.

Plans, specifications, and blueprints $26,040

Architects' fees for design and supervision 101,680

The building is estimated to have a 40-year life from date of completion and will be depreciated using the 150% declining-balance method.

To finance construction costs, Martinez borrowed $3,720,000 on March 1, 2020. The loan is payable in 10 annual installments of $372,000 starting on March 1, 2021, plus interest at the rate of 10%. Martinez's weighted-average amounts of accumulated building construction expenditures were as follows.

For the period March 1 to December 31, 2020 $1,612,000

For the period January 1 to September 30, 2021 2,356,000

(a)

a schedule that discloses the individual costs making up the balance in the land account in respect of land site number 101 as of September 30, 2021.

MARTINEZ CORPORATION

Cost of Land (Site #101)

As of September 30, 2021

Cost of Land and Old Building

$620,000

Real Estate Broker's Commission

44,640

Legal Fees

7,440

Title Insurance

22,320

Removal of Old Building

66,960

Cost of Land

$761,360

(b)

a schedule that discloses the individual costs that should be capitalized in the office building account as of September 30, 2021.

MARTINEZ CORPORATION

Cost of Building

As of September 30, 2021

$

$

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operational Risk Management

Authors: Mark D Abkowitz

1st Edition

0470256982, 9780470256985

More Books

Students also viewed these Accounting questions

Question

Values: What is important to me?

Answered: 1 week ago

Question

Purpose: What do we seek to achieve with our behaviour?

Answered: 1 week ago