Question
On January 1, 2020, Mechathon Inc. accepted a long-term construction contract to build a condominium with a total contract price ofP27,000,000. For the two years
On January 1, 2020, Mechathon Inc. accepted a long-term construction contract to build a condominium with a total contract price ofP27,000,000. For the two years ended December 31, 2020 and 2021, the following data were provided by Mechathon Inc.:
12/31/2020 12/31/2021
General administration cost which is not reimbursable under
the contract for the year
P1,800,000 P2,700,000
Site labor costs including site supervision for the year
3,150,000 4,500,000
Selling costs for the year 3,600,000 900,000
Cost of direct materials used in construction for the year
2,250,000 3,060,000
Estimated cost to complete the condominium at year end
3,600,000 3,240,000
Mechathon Inc. billed its client 30% during 2020 and 40% during 2021. The outcome of the construction contract can be estimated reliably.
- What is the balance of the Construction in Progress in excess of Progress Billings / (Progress Billings in excess of Construction in Progress) to be presented in the Mechathron's December 31, 2021 Statement of Financial Position?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started