Question
On January 1, there were two jobs in process, no. 200 and no. 300. The following costs were applied to these jobs in the prior
On January 1, there were two jobs in process, no. 200 and no. 300. The following costs were applied to these jobs in the prior year:
Job No. | ||
200 | 300 | |
Direct material | $ 5,000 | $ 8,000 |
Direct labor | 4,000 | 3,000 |
Overhead | 4,400 | 3,300 |
Total | $13,400 | $14,300 |
During January, the following transactions took place:
* | Raw material costing $40,000 was purchased on account. |
* | Jobs #424, #525 and #626 were started and the following costs were applied to them: |
JOB | |||
424 | 525 | 626 | |
Direct materials | $3,000 | $10,000 | $7,000 |
Direct labor | 5,000 | 6,000 | 4,000 |
* | Job #200 and Job #300 were completed after incurring additional direct labor costs of $2,000 and $4,000, respectively |
* | Wages paid to production employees during January totaled $25,000. |
* | Depreciation for the month of January totaled $10,000. |
* | Utilities bills in the amount of $10,000 were paid for operations during December. |
* | Utilities bills totaling $12,000 were received for January operations. |
* | Supplies costing $2,000 were used. |
* | Miscellaneous overhead expenses totaled $24,000 for January. |
Actual overhead is applied to individual jobs at the end of each month using a rate based on actual direct labor costs.
Required:
1 | Determine the January overhead rate. |
2 | Determine the cost of each job. |
3 | Prepare a statement of cost of goods manufactured. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started