On January 6, Year 1, Mount Jackson Corporation purchased a tract of land for a factory site for $825,000. An existing building on the site
On January 6, Year 1, Mount Jackson Corporation purchased a tract of land for a factory site for $825,000. An existing building on the site was demolished and the new factory was completed on October 11, Year 1. Additional cost data are shown below: Construction cost of new building $ 1,000,000 Real estate and attorney fees 18,200 Architect fees 84,000 Cost to demolish old building 77,100 Salvage recovery from old building (13,000 ) Which of the following are the capitalized costs of the land and the new building, respectively? Multiple Choice
A $843,200 and $1,148,100
B $920,300 and $1,071,000
C $825,000 and $1,166,300
D $907,300 and $1,084,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started