Question
On July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000
On July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion on October 2019. The contract contains a penalty clause to the effect that the other party was to deduct P35,000 from the contract price for each week of delay. On the other hand, if the contractor was able to finish the building earlier than agreed, it will be rewarded an amount equal to P50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2018, the estimated costs of particular construction material amounting to P520,000 were bought for P780,000. The increase in the contract price related to this cost escalation was approved by the client. Completion was delayed for 4 weeks. The records show:
2017 2018 2019
Costs incurred P1,750,000 6,440,000 1,085,000
Estimated cost to complete 7,000,000 1,810,000 --
Progress billings 1,400,000 15,225,000 4,200,000
1. What is the Original Contract Price 2017?
2. What is the Original Contract Price 2018?
3. What is the CIP net as of 2018?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started