Question

1 Approved Answer

On July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000

On July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion on October 2019. The contract contains a penalty clause to the effect that the other party was to deduct P35,000 from the contract price for each week of delay. On the other hand, if the contractor was able to finish the building earlier than agreed, it will be rewarded an amount equal to P50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2018, the estimated costs of particular construction material amounting to P520,000 were bought for P780,000. The increase in the contract price related to this cost escalation was approved by the client. Completion was delayed for 4 weeks. The records show:

2017 2018 2019

Costs incurred P1,750,000 6,440,000 1,085,000

Estimated cost to complete 7,000,000 1,810,000 --

Progress billings 1,400,000 15,225,000 4,200,000

1. What is the Original Contract Price 2017?

2. What is the Original Contract Price 2018?

3. What is the CIP net as of 2018?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Karen BraunWendy Tietz

3rd Edition

0132890542, 978-0132890540

More Books

Students also viewed these Accounting questions

Question

2. Ask questions, listen rather than attempt to persuade.

Answered: 1 week ago