Question

1 Approved Answer

On July 1, 2017, Indigo Construction Company Inc. contracted to build an office building for Gmbel Comp for a total contract price of$1,910,000. On July

On July 1, 2017, Indigo Construction Company Inc. contracted to build an office building for Gmbel Comp for a total contract price of$1,910,000. On July 1, Indigo estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019.

12/31/17 12/31/18 12/31/19

contract costs incurred to date $302,000 $1,105,500 $2,115,200

estimated costs to complete the contract $1,208,000 904,500 0

Billings to Gumbel 300,000 1,080,000 1,860,000

(a) using the percentage of completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended Dec 31, 2017,2018, and 2019 (ignore income tax)

(b) using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the year ended in Dec 31, 2017, 2018, and 2019. (ignore income taxes)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

16th edition

1118742974, 978-1118743201, 1118743202, 978-1118742976

More Books

Students also viewed these Accounting questions