On July 1, 2020, Drenz Company purchased land and incurred other costs relative to the construction of
Question:
On July 1, 2020, Drenz Company purchased land and incurred other costs relative to the construction of a new warehouse. A summary of economic activities is listed below.
Purchase price 925,000
Title insurance 7,500
Legal fees to purchase land 5,000
Cost of razing old building on lot 42,500
Proceeds from sale of salvageable materials 6,000
Property taxes, January 1, 2019 to June 30, 2019 15,000
Cost of grading and filling building site 45,000
Cost of building construction 3,100,000
Interest in construction loan 60,000
Cost of constructing driveway 400,000
Cost of parking lot and fencing 60,000
Based on the above data, determine the cost of the following:
1.Land
a.P997,500
b.P1,034,000
c.P952,500
d.P982,500
2.Building
a.P3,196,500
b.P3,160,000
c.P3,205,000
d.P3,256,500
3.Land Improvements?
a.P400,000
b.P460,000
c.P505,000
d.P60,000