On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $260 million. The expected

On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $260 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

2018 2019 2020
Costs incurred during the year $ 60 $ 80 $ 65
Estimated costs to complete as of December 31 140 60

Required: 1. Compute the revenue and gross profit will Sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2019 are $110 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2019 using the percentage of completion method.

image text in transcribed

image text in transcribed

image text in transcribed

2018 2019 2020 Construction revenue Construction expense Gross profit (loss) Construction revenue Construction expense Gross profit (loss) Construction revenue Percentages of completion Choose numerator Choose denominator complete to date 100.00% 2018 To date Recognized in prior years Recognized in 2018 S 0 2019 To date Recognized in prior years Recognized in 2019 S 0 2020 To date Recognized in prior years Recognized in 2020

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Security Audit Guidebook NIST SP 800-171

Authors: Mark A Russo CISSP-ISSAP CISO

1st Edition

1726674908, 978-1726674904

More Books

Students also viewed these Accounting questions

Question

Develop a program for effectively managing diversity. page 303

Answered: 1 week ago

Question

List the common methods used in selecting human resources. page 239

Answered: 1 week ago