On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $250 million. The expected

On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $250 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

2021 2022 2023
Costs incurred during the year $ 80 $ 40 $ 30
Estimated costs to complete as of December 31 120 30

Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $120 million instead of $30 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion. image text in transcribed

image text in transcribedimage text in transcribed

Actual costs to date Estimated total costs 0 2021 2022 2023 = 0 0 2021 Recognized in prior years To date Recognized in 2021 $ 0 Construction revenue Construction expense Gross profit (loss) 0 AEA $ $ 2 0 2022 Recognized in prior years To date Recognized in 2022 $ 0 Construction revenue Construction expense Gross profit (loss) $ $ GA 0 $ 0 2023 Recognized in prior years To date Recognized in 2023 $ Construction revenue Construction expense Groce nrofit (local AEA 0 0 $ $ NE Year 2021 2022 Revenue recognized million Gross Profit (Loss) recognized million million million million 2023 million 11 Percentages of completion Choose numerator Choose denominator Actual costs to date Estimated total costs $ % complete to date 2022 120 II 0 2022 Recognized in prior Years To date Recognized in 2022 0 Construction revenue Construction expense Gross profit (loss) $ $ $ 0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cornerstones of Managerial Accounting

Authors: Mowen, Hansen, Heitger

3rd Edition

324660138, 978-0324660135

More Books

Students also viewed these Accounting questions