On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (\$ in millions): Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $150 million instead of $90 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. (Enter your answers in millions. Loss amounts thould be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract ar irminn esondanenn ramanize ravenue nver time accordina to dercentage of completion. (Enter your answers in millions. Loss amounts inal answer.) Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021,2022 , and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $150 million instead of $90 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. (Enter your answers in millions. Loss amounts should be indicated with a minus sign.) Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $150 million instead of $90 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Suppose the estimated costs to complete at the end of 2022 are $150 million instead of $90 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 using the percentage of completion method. (Enter your answers in millions. Use percentages as calculated and rounded in the table below to arrive at your final answen.)