Question
On June 30, 2019, Tier One Construction Company began construction of a new arena in Seattle, which will host the home games of the new
On June 30, 2019, Tier One Construction Company began construction of a new arena in Seattle, which will host the home games of the new NHL team, the Seattle Kraken.
Tier One agreed to complete the stadium by June 30, 2021, at a fixed price of
$ 1,500,000,000.Tier One has a fiscal year that ends on December 31, and will recognize revenue on the contract over time, and plans on using the ratio "Costs Incurred"/"Estimated Total Costs" to measure percentage of completion.Information related to the contract at various points in time is as follows:
Dec. 31, 2019Dec. 31, 2020June 30, 2021
Cumulative Costs Incurred$ 300,000,000$ 910,000,000$ 1,325,000,000
Estimated Remaining Costs900,000,000390,000,0000
Cumulative Amount
Billed to Customer400,000,000800,000,0001,500,000,000
A. (1)Based on the information provided above, Tier One Construction will report an
ASSET / LIABILITY (circle one) in the amount of $ _____________
on their December 31, 2019 Balance Sheet related to the difference between
"Construction in Progress" and "Billings on Construction in Progress".
B. (1)How much revenue will Tier Once Construction report on this contract for their
Fiscal year ending December 31, 2020?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started