On March 1 , 2 0 2 0 , Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total

On March 1,2020, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,350,000. The building was completed by October 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020,2021, and 2022 are given below:
\table[[,2020,,2021,,2022],[Contract costs incurred during the year,$2,939,400,,$2,309,400,$2,041,200,],[Estimated costs to complete the contract at 1231,3,450,600,,2,041,200,-0-,],[Billings to Fabrik during the year,3,190,000,,3,480,000,1,680,000,]]
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31,2020,2021, and 2022.(Ignore income taxes.)(If answer Is O, please enter 0. Do not leave any fields blank. Enter loss using elther a negative sign preceding the number e.g.-45 or parentheses e.g.(45).)
2020
$
$
%
$
2021
$
$
$
$
2022?
$
2021?
$
\table[[$

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Create a Fishbone diagram with the problem being coal "mine safety

Answered: 1 week ago